As at 30 September 2020, the IPPs dashboard is as follows

TechnologyNumber of projectsLocation of PlantsInstalled Total Capacity (MW)Operational
Solar552x Manicaland

12x Mash East

5 x Masvingo

1 x Mash Central

4 x Harare

9 x Midlands

3 x Mat North

6 x Mat South

2 x Bulawayo

11 x Mash West

1190.88 MW5
Coal-fired54x Mat North

1x Midlands

5650 MW
Mini Hydros222 x Masvingo

20 x Manicaland

97.02 MW9
Bagasse (Co-gen)31 x Manicaland

2 x Masvingo

92.3 MW3
Gas Fired1Manicaland345 MW
Diesel1Mashonaland East200 MW
Biomass1Manicaland0.5MW
Solar/diesel1Mat South2.25MW1