As at 30 September 2020, the IPPs dashboard is as follows

Technology Number of projects Location of Plants Installed Total Capacity (MW) Operational
Solar 55 2x Manicaland

12x Mash East

5 x Masvingo

1 x Mash Central

4 x Harare

9 x Midlands

3 x Mat North

6 x Mat South

2 x Bulawayo

11 x Mash West

1190.88 MW 5
Coal-fired 5 4x Mat North

1x Midlands

5650 MW
Mini Hydros 22 2 x Masvingo

20 x Manicaland

97.02 MW 9
Bagasse (Co-gen) 3 1 x Manicaland

2 x Masvingo

92.3 MW 3
Gas Fired 1 Manicaland 345 MW
Diesel 1 Mashonaland East 200 MW
Biomass 1 Manicaland 0.5MW
Solar/diesel 1 Mat South 2.25MW 1